R-APDRP Scheme

R-APDRP

Restructured Accelerated Power Development & Reforms Programme is sponsored by Power Finance Corporation. Total 39 towns having more than 30,000 Population are covered under this scheme.


Part-A

Establishment of baseline data& IT application for energy accounting/ auditing & IT based consumer service centre(sanctioned amount Rs. 93. 69 crores)

  • Full Go-Live Towns-Atrauli, Bhartana, Sikandrarao, Kosikalan & Jalesar.
  • MBC Go-Live Towns Tundla, Hathras, Sadabad, Etah, Jhansi, Etawah, Farrukhabad, Vrindavan, Aligarh, Firozabad, Mathura, Jaulan, Hamirpur.
  • Remaining 21 towns are scheduled for MBC Go-Live/Full Go-Live till March 2014.

Part-B

System improvement related works like renovation , modernization, reconductering ,load bifurcation, feeder separation , load balancing , HVDS, ABC, Replacement of energy meter, Installation of capacitor banks& mobile service centre.

Restructured Accelerated Power Development & Reforms Programme is sponsored by Power Finance Corporation. Total 39 towns having more than 30,000 Population are covered under this scheme.

  • For 33 Towns under R-APDRP Part-B works are having Sanctioned cost of Rs.436.25 Crore, Supply and Erection works are in progress
  • For 3 Towns (Aligarh, Firozabad & Jhansi) under R-APDRP Part-B SCADA are having Sanction cost of Rs. 516.18 Crore. Tender for these towns is under process of finalization. DPR for Revised cost has been submitted to PFC for Approval.
  • For 3 Towns (Mathura, Vrindavan & Chjitrakoot) under R-APDRP Part-B Underground works in Religious Town are having Sanctioned cost Rs. 406.90 Crore, Price bid has been opened and tender is under process of finalization.